Six Accra flood-control projects stall over Finance Ministry clearance
Ibba Lanka · Nov 19, 2026

Works, Housing and Water Resources Minister Ahmed Ibrahim told Parliament on Wednesday that construction cannot start on the six schemes of GARID (Greater Accra Resilient and Integrated Development) until the Finance Ministry issues the commitment authorisation.
Six flood-control projects meant to protect Accra from floods are stuck at the contract stage until the Finance Ministry grants financial clearance.
Works, Housing and Water Resources Minister Ahmed Ibrahim told Parliament on Wednesday that construction cannot start on the six schemes of GARID (Greater Accra Resilient and Integrated Development) until the Finance Ministry issues the commitment authorisation.
He was answering MPs' questions on the floor of the House about the state of GARID and the government's efforts against perennial flooding in the capital. MPs on the Works and Housing Committee recently inspected flood control projects to press for progress.
The six schemes waiting for clearance Rebuilding the Abossey Okai Bridge Building the Atomic East detention pond Building the Atomic West detention pond Improvement works on the Alajo drain Nima drain works repackaged for re-tender Installing the Accra Flood Early Warning Systems All six are at the tendering and contract-award stage, the minister said.
The Nima-Paloma drainage contract has been terminated outright. Mr Ibrahim said it would be repackaged and awarded to a new contractor once the financial commitment is secured.
When the contract was ended, excavation works had reached 13 per cent, demolition of the existing drain 25 per cent, and casting of the concrete base and walls 9.7 and 9.5 per cent.
Meanwhile, the ministry has hired Dredge Masters to clear silt out of the Nima-Paloma drain so that stormwater can flow, with local measures in place for communities upstream and downstream of the unfinished works.
"Further, some additional local measures were put in place to reduce the exposure of adjoining communities at the upstream and downstream sections of the Nima drain where the previous contractor had initiated works but had not completed," he said.
The ministry is also talking to stakeholders, including the World Bank, about the best procurement route for the new Nima contractor. GARID itself is a World Bank-funded programme that combines drainage works with solid-waste and community upgrading in the Odaw basin.
Parliament approved a further $150 million World Bank loan for the project, after a disputed vote in which the minority raised accountability questions about earlier spending. The minister said GARID is pursuing structural and non-structural measures across the Odaw basin.
The stakes were clear in June, when floods swamped parts of Accra and poultry farmers hit by the June 29 floods received GH¢700,000 in support. Until the Finance Ministry signs off, the six new defences stay on paper.